Iyubakwa ry’ibiro bya Arusha


Amakuru mashya: ibiro bishya by’Ishami ry’Arusha byatashywe ku mugaragaro ku itariki ya 25 Ugushyingo mu muhango wayobowe na Nyakubahwa Samia Suluhu Hassan, Visi Perezida wa Repubulika Yunze Ubumwe ya Tanzaniya. Itangazo rigenewe abanyamakuru



Muri raporo ye yo ku itariki ya 16 Mutarama 2013 yageneye Inteko Rusange, Umunyamabanga Mukuru w’Umuryango w’Abibumbye yashimangiye ko imiterere yihariye y’ibisabwa birebana na gahunda, imikorere n’umutekano bya MICT byatumye biba ngombwa ko hubakwa ibiro bishya by’Ishami ryayo ry’Arusha, aho icyicaro cya TPIR kiri.

Guverinoma ya Repubulika Yunze Ubumwe ya Tanzaniya yemeye gutanga ku buntu ahantu hazubakwa ibiro bya MICT, no kuhageza ibikorwaremezo n’ibindi bintu by’ibanze bizahakenerwa.

Ahantu heza kurusha ahandi hatoranyijwe ni ahitwa Lakilaki, mu nkengero z’umugi w’Arusha n’ikibuga cy’indege cyawo.

Iyo nyubako izubakwa ku buryo ijyana neza n’imiterere idahanamye cyane y’ako gasozi. Uruhande rutariho amazu rw’iyo mbuga, izengurutswe n’amazu ku zindi mpande eshatu, ruzatuma Umusozi wa Meru uri mu majyaruguru ugaragara neza. Imbata y’iyo nyubako muri rusange igaragaza kamere nyirizina ya MICT, ni ukuvuga urwego rwibona nk’icyitegererezo rukoresha abakozi bake, rudasesagura kandi rutunganya neza imirimo yo gutanga ubutabera mpanabyaha bwo mu rwego mpuzamahanga. Ayo mazu atatu si manini cyane kandi imyubakire yayo iteye ku buryo uwashaka kuyihindura bitamugora, bityo akaba yahindurwa bitewe n’inshingano zidahoraho za MICT. Ibyo bikaba bihuje n’intumbero y’Inama Ishinzwe Amahoro ku Isi yo kugira MICT urwego ruto rudahoraho, rukora neza kandi rudasesagura.

Uyu mushinga wubahiriza imikorere myiza ngenderwaho mu bwubatsi bwateye imbere mu guhanga imbata z’inyubako no kubaka mu buryo bwubahiriza ibidukikije. Ibi bizatuma imikoreshereze y’amashanyarazi, amazi n’ibindi biyagendaho bigabanuka, bityo amafaranga azagenda kuri ayo mazu mu gihe kirambye n’ibyuka bihumanya ikirere bizagabanuke. Ibyo kandi bizagabanya imyanda ikomoka ku mirimo y’ubwubatsi binateze imbere imigenzo myiza ikurikizwa mu bwubatsi bwo mu karere.

Iyo nyubako izaba yujuje ibisabwa byose n’Amasezerano ku burenganzira bw’ababana n’ubumuga. Abantu bose bazashobora kugera mu bice byose by’iyo nyubako no kubyinjiramo, by’umwihariko abashakashatsi na rubanda rusanzwe, harimo n’ababana n’ubumuga bw’ingingo z’umubiri, ubwo kutumva, kutabona cyangwa ubwo mu bwonko.

Kurangiza uyu mushinga bizafata imyaka igera kuri ine, naho amafaranga azawutangwaho muri rusange azaba akabakaba amadorari y’Abanyamerika 8 700 000.

Ingengabihe y’imirimo yerekeye uwo mushinga

Project timeline

Aho imirimo y’ubwubatsi igeze

The site of Lakilaki  before construction works started.
The local construction company Jandu Plumbers Ltd. took over the site, mobilised the site office atop of the hill and officially commenced works at the end of February. Tanzania made progress with the construction of a temporary access road to the site, which had started earlier in February.
After having completed the setting-out of the site boundary and the building survey layout, Jandu started the excavation of the building foundation and the perimeter fence footings. Tanzania completed the temporary access road and provided electricity to the site.
The contractor fully completed the mobilization; excavation is in progress to prepare the foundation works for the office building.
The bulk excavations for all buildings - the office, archives and courtroom, as well as the ancillary pump house and pedestrian security buildings - have been completed. Foundation works are in progress for the office and archives buildings.
The foundation works for the office building have been completed, and are in progress for the archives, the court and the ancillary buildings. Preparation for the construction of the ground floor of the office has begun.
The construction of the ground floor of the office building is ongoing. The foundation of the archives and courtroom buildings have been completed and preparations for the construction of their respective ground floor have begun.
The construction of the ground floor of the three buildings - the office, the archives and the courtroom - is ongoing.
Construction of the columns and walls of the archives and court buildings have commenced.
Construction of the columns and walls of the three main buildings continue to progress and the preparatory works for the roof of the archives and court buildings have commenced.
The structure of the archives building has been completed.  The structure of the court building is also complete with the exception of its conical element whose construction is in progress. Finally, the structure of the ground floor of the office building has been completed and construction of the first floor is underway.
The fit-out of the interior of the archives and the courtroom buildings has started. The construction of the upper floor of the office building is ongoing.
As the interior fit-out of the buildings continues, the earthworks for the parking lot, the internal road, and the perimeter fence have began.
As the interior fit-out of the buildings continues, the external works are ongoing, with the installation of the perimeter fence and the construction of the parking lot and the internal road. The excavation of the underground ducting and the courtyard has also begun.
As interior and exterior fit-out progresses, external works are on-going. The formation of the courtyard, installation of underground ducting and drainage system has been completed, while the construction of the parking and internal road continues.
As interior and exterior fit-out continues to progress, external works are on-going. The courtyard is ready for finishing touch.  The tree, a central feature of the courtyard, has been planted.
Interior fit out and external land formation continue to progress. Benches have begun to be installed in the courtyard, and the staircase and ramp between the courtyard and office building await final finishes.
Interior and exterior finishes continue to progress. The preparatory work for the installation of the curtain wall - the last structural element of the project - has been completed.